Commissioning is where a correct design becomes a working room. The sequence below is ordered so that each step depends only on the steps before it — which means a failure is localised rather than hunted.
Confirm every cable is the cable specified, terminated to standard, and labelled at both ends. Confirm active optical cables run source-end to source-end. Confirm CAT runs are within their distance budget and that the shield is bonded as designed.
Verify rack ventilation and power distribution. A matrix that thermally throttles at hour six of a board meeting fails in the least forgiving way available to it.
Power the matrix with no sources connected. Confirm the web interface is reachable and firmware is current across the estate. Connect one source. Confirm it appears, negotiates, and routes to one display.
Add sources one at a time. Add displays one at a time. Every fault discovered this way has exactly one cause.
Set the EDID strategy for the room before testing protected content. Confirm each source is offered the format the room requires. Then introduce a protected source and confirm authentication across every output, including the recorder if one exists.
Cold-boot the whole system and confirm it authenticates again. The handshake that works on a warm system and fails on a cold one is the handshake that fails on Monday.
Confirm every control surface performs every documented function, including display power, input select, and volume. Confirm Dante subscriptions persist across a power cycle. Confirm the room recovers unaided.
Then write it down. Record the EDID mode per input, the control addresses, the Dante device names, the firmware versions, and the serial numbers. Register the warranty. The room is commissioned when someone who has never seen it can support it.