An extender datasheet says 70 metres. The corridor measures 68. The project proceeds — and at commissioning the far display blinks once an hour. Nobody lied. A reach figure is a laboratory sentence: this distance, at this format, over this cable class, terminated this way. The figure travels into the field; its conditions often do not. Reading both halves is a five-minute skill that prevents the most expensive kind of surprise.
The three subtractions
Cable class and construction. HDBaseT reach figures assume the specified category — shielded, solid-core, correctly bonded. Substituting a lower class or stranded patch-style cable does not fail immediately; it converts margin into hope. The figure survives only on the cable it was measured on.
Connection points. Every patch panel and coupler spends link budget. Two patch points on a run near the limit can be the whole difference — which is why a near-limit run is terminated directly, as our cabling guide and the Commissioning Record both insist.
Format. Reach and bitrate trade against each other. A link comfortable at 1080p can be marginal at 4K60 4:4:4 — some products state two reach figures for exactly this reason, and both are true. Specify reach at the format the room will actually run, not the format the demo ran.
Specify the pair, prove the pair
The professional habit is to write distance with its conditions into the tender — 70 m at 4K60 over shielded CAT6A, directly terminated — and then to prove the installed link at that format during commissioning, in sequence, on the record. Where the subtraction leaves no margin, change the transport rather than the truth: that is what fibre and the networked tiers are for.
The figure is honest. The room is the footnote. Commissioning is where the two are made to agree — in writing.